Melamchi project will be completed before mid-July: Khatri

Kathmandu, December 30

Amid uncertainty about completion of Supply (MDWSP), the executive director of the has claimed it will be completed by July 15.

Speaking at the Development and Technology Committee under the Federal today, Tiresh Prasad , executive director of Melamchi Water Supply Development Board, claimed that the water from Melamchi will be brought to Sundarijal by the end of June.

He said that 95.12 per cent of physical of the project has been completed.

Khatri informed that out of 32 gates of the project, two have been installed. “We plan to instal 17 gates by mid-July,” Khatri said, adding that installation of the remaining gates could be carried out without affecting the schedule of launching the project.

On September 29, the had awarded Chinese contractor named Sinohydro to complete the remaining works of the project by ongoing fiscal.

Read the full article on The Himalayan Times.

Read Previous

Not much to celebrate for the economy in 2019

Read Next

About 72pc of ADB’s portfolio Focuses on infrastructure

Got any Comments/ Questions?